December 22, 2024

WCB gear pump installation

WCB gear pump installation and precautions
  
WCB gear pump gear pump as one of the most common type of pump installation is relatively simple, the following are some of the considerations in the installation process
  
First, the installation of WCB gear pump should pay attention to the process:
  
1, WCB gear pump installation is good or bad, the smooth operation of the pump and the life has a very important impact, so the installation and calibration must be carefully carried out, not sloppy.
  
2, WCB gear pump suction pipe installation height, length and diameter should meet the calculated value, and strive to be brief, reduce unnecessary losses (such as elbows, etc.); Rotor pump and ensure that the pump does not exceed its work permit cavitation margin.
  
3, WCB gear pump suction and discharge piping should be scaffolding. Pump is not allowed to withstand the load on the pipeline.
  
4, WCB gear pump installation location should be spacious enough to facilitate maintenance work.
  
Second, WCB gear pump installation method and order:
  
1, the unit on the foundation buried in the bolt, between the base and the base, with a pair of wedge pad with calibration.
  
2, release the coupling large, respectively, with the spirit level on the pump shaft and the base, by adjusting the wedge pad, the unit level correction, appropriate tighten the anchor bolts to prevent ambulation.
  
3, the correction of the concentricity of the pump shaft and the motor shaft, on the outer diameter of the coupling path, allowing 0.1 mm deviation; two coupling plane clearance should be guaranteed 2 to 4 mm, (small pump to take small) gap to be uniform, Tolerance of 0.3 mm.
  
4, pick up the pipeline and determine the direction of motor rotation, then connect the coupling, and then check the concentric ax again axis.
  
5, the actual test run in the unit after 2 to 3 hours for the final inspection, if no bad phenomenon, then that the installation of qualified. Check the temperature and vibration of the bearing during commissioning as follows:
  
6, in the installation process, in order to prevent debris falling into the machine, all the holes of the unit should be covered.
  
7, to prevent debris in the pipeline into the gear pump, the newly installed pipeline, the pump should be installed in the plastic filter, the effective cross-section should be greater than 2 to 3 times the suction pipe cross section.

Small Roll Paper

Grams:29/31/38/42/52/62/82/95

width:0.914m,1.118m,1.2m,1.3m,1.5m,1.52,1.6m,1.62m,1.7m,1.8m,1.82m,2.0m and so on.

length:100m,200m,300m,500m,800m,1000m could as your requirement.


As a general agent of Xianhe in the southern region of China, we have a significant share in the domestic market and also export to overseas markets, covering multiple countries and regions around the world, including Southeast Asia, the Middle East, Europe, and North America.

Small Roll Paper,High Quality Polyester Paper,Sublimation Paper Printing Machine,Printing Paper Bag

Guangzhou YESUN Digital Technology Limited , https://www.sublimationpaperfactory.com